Recently, the project for the construction of administrative infrastructure in the city of Cuito, in Angola's Bié province, has entered the phase of pouring concrete for the project's raft slabs.
The project's B3 office building is a two-storey building above ground, covering a total area of 22,547 square meters, with a construction area of 6,242 square meters for the B3 office building and 272 square meters for the T1 technical room.
The construction content covers
B3 office building (two-storey, partial pitched roof), T1 technical room and water supply pool (above ground), outdoor road, fence wall and janitor's room, etc. The construction involves foundation works, structural works, architectural works, decoration works, strong and weak electricity works, water supply and drainage works, ventilation works, elevator works, fire-fighting works and other specialties; the outdoor works include road works, outdoor rainwater and sewage works, and outdoor lighting works. Outdoor works include road works, outdoor rainwater and sewage works, outdoor lighting works, etc.
Since the project entered the field in May 2023, in the face of the project no reference point, the local market, the main construction materials, equipment types are not complete and other unfavorable factors, the project department calmly and actively respond to the project gradually and item by item to solve the project to start the prerequisites for the smooth implementation of the project to make adequate preparations; the project leadership team combined with the project's actual situation, the development of the implementation of various programs and vigorously promote the project's good operation. The leadership team of the project department has formulated various implementation programs according to the actual situation of the project and strongly promoted the good operation of the project.
The project department takes "compressed construction period, cost saving" as one of the themes, makes scientific planning, implements the optimal input ratio of manpower, material and machine, seeks benefits from technology, quality, safety and business, actively explores localized construction, comprehensively improves the management level, ensures the construction safety, guarantees the quality of construction, and thus guarantees the efficient operation of the project.
Up to now, the project department has opened the situation of simultaneous commencement of unit works and flow operation of sub-projects, and actively responded to the company's "on-site production to support the market development" requirements, and planned the preparatory work in advance. By reducing the technical preparation time, shortening the process transformation time, holding technical symposiums, implementing the sample system, and improving the one-time passing rate of process acceptance as the entry point, the project department has basically realized the goal of completing the contract amount in percentage equal to the percentage of the completion period, which has laid the foundation for realizing the project's high performance standard.
In the next step, the project department will continue to keep a clear idea, adhere to the principle of "safety first, quality first", and complete the new phase of work in a positive, practical and pragmatic way.