DCCP cement clinker production line and power plant project in Iraq, including a new dry-process cement production line with a daily capacity of 6,000 tons of clinker and a heavy fuel oil captive power plant, with a design life of 25 years, a construction period of 2 years, and an operation and maintenance period of 7.5 years. on March 8, 2023, the owner officially issued the order for the commencement of the construction work. We undertook the project's temporary construction, road and part of the civil construction work.
Currently completed and operational are the labor camps in Areas B, C and D, the Elegant House and Frame House dormitories in Area A, and the Owners' Camp.
On-site road projects
Due to the rainy season, in order to ensure the quality and progress of construction and minimize the impact of the rainy season on the construction, the project team adjusted the construction plan in time, worked overtime to catch up with the schedule, and has paved about 1.2 kilometers of water stabilized layer road surface.
Auxiliary/Gypsum/Mixed Material Pre-Homogenization Yard Project
When the site is in progress: the concrete pouring of 1-11 axle net frame foundation is completed, and the earth backfilling is completed; the concrete pouring of 2-11 axle track foundation is completed, and the reinforcement bars of the track floor beam and installation of the track and embedded parts are now being tied; the foundation of the 82-meter retaining wall of DLQ-1a is cleaned up and completed, and it is ready for pouring of the bedding layer.
Heavy Oil Tank Foundation Project
This project is essentially complete with the remaining bulkhead within the firewall, backfilling of the firewall foundation and preparation of the tank foundation for gravel bedding.
Cement Dosing Station Project
This project is a frame structure, the total height of the concrete structure is 13.5 meters, divided into two floors. Current construction progress: the first floor of full scaffolding is completed, and the column reinforcement bars are now being tied.
Limestone Pre-Homogenization Yard/Pure Limestone Depot Project
The site is undergoing track beam support school formwork, corridor erection of full scaffolding and reinforcement formwork and tying of reinforcing steel.
After the project is completed and put into operation, it will provide high-quality construction materials for Iraq and create local employment opportunities, which will play an important role in promoting Iraq's industrial development and improving people's livelihood.
The project engineering process is complex
Tight schedule and large volume of work
In order to ensure the overall construction progress
The Iraqi project team worked overtime without letting up
Adhering to last year's pioneering spirit
Going all out to promote the construction of key projects
Running at full power to fulfill the first journey in the new year.