July Letter

Page view

Dear Kwang Jin family:

      I am very happy to meet you.

      A thousand sails dare to be the first, a hundred boats compete for the first. In July, full of yellow change in the mountains, high and refreshing autumn, it is one of the few good weather in Zambia, and also the beginning of the last quarter before the rainy season comes. Recently, all projects in Zambia are grasping the time, concentrating their efforts, seizing the golden period, accelerating the progress of project construction, and striving for new achievements in the current year.

I would like to report to the family on the progress of the project:

The chipapa school is a social responsibility project of Kefu Gorge Hydropower Station undertaken by Guangjin Construction. The school project started in July last year, and the construction content includes 11 single buildings. chipapa school is a local high school, with more than 300 students, the original school building only has two teaching buildings, no dining hall, students can only eat in the open air; the original school building has two small dormitories for one boy and one girl, which can only accommodate more than 70 people. After the delivery of this expansion, the number of students in the school can reach 500, the accommodation of students can reach more than 250 people, the expansion of the new boys and girls bathrooms, restaurants, libraries, laboratories and other supporting facilities.

As of July 25th of this year, all classroom monoliths are finished and the next step is to hand over the work. The laboratory unit is installing electrical equipment, the overall progress is 90% complete, masonry, stucco, paint, water and electricity work has been completed. The girls' dormitory is in the process of installing closet doors and windows. 80% of the overall progress has been completed, and masonry, stucco, paint, and plumbing work have all been finished. The women's bathroom is making terrazzo flooring, tiling, and painting work. 70% of the overall progress has been made, and masonry, painting, and roofing have been completed.

The boys' dormitory is being painted and doors and windows are being installed at an overall progress of 70%, and the boys' bathroom is being painted at a progress of 60%. The school clinic is being painted with an overall progress of 55%, the library roof and ceiling are under construction with an overall progress of 50%, the cafeteria masonry is completed and painting and roofing is being done with an overall progress of 40%, the No. 1 teacher's dormitory is having its walls masoned with an overall progress of 25%, the No. 2 teacher's dormitory is having its excavation completed and is undergoing the construction of the foundation.

The campus infrastructure upgrades are concurrent and intersecting.

Tight schedule and many procedures

In order to ensure high quality and efficient completion of the construction task, Guangjin team

Rushing to meet the schedule

After the completion of the project, the learning environment of students will be greatly improved.

Provide a safer and more scientific education environment

It will also strongly promote the development of local education

We look forward to the results and changes that will be brought to the campus after the construction is completed.