Dear family members of GuangJin:
I am very happy to meet you after the summer, and I am very happy to meet you in the early fall. In August, the harvest is brewing, the Iraqi family letter came late, only because the project all staff are in full swing to grab the progress, scrambling to ensure delivery. The Guangjin team carefully controlled every process and material, and continued to superimpose the requirements for quality control. Now, the brand-new appearance of the Iraqi model school has gradually unfolded, and the whole project process has been transformed into a letter to every family member who is full of expectations, delivering a good message about the project.
We would like to present the latest construction progress broadcast for our families:
School 101: handrail railing welding and installation is 98% complete, outdoor concrete pouring for bulk water is 50% complete, indoor distribution box installation and testing of wiring is 50% complete, indoor paint painting is 85% complete, outdoor primer painting is 100% complete, external wall plastering of annexed rooms is 100% complete, wall and floor tiles of annexed rooms and bathrooms are 10% complete, installation of light fixtures and sanitary fittings is 85% complete, galvanized 60%, 20% of the fence wall plastering, 50% of the concrete pouring for the roof of the front fence wall, 60% of the fence wall masonry, 35% of the outdoor curb installation, 40% of the outdoor drainage pipe construction, and 20% of the concrete pouring for the outdoor inspection well.
99 Schools: first floor masonry 75% complete, outdoor steel welding 100% complete, outdoor backfill 68% complete, second floor plastering 90% complete, second floor putty construction 50% complete, second floor ceiling keel rack installation 50% complete, first floor roof JASS 100% complete, first floor window over-beam formwork installation 90% complete, outdoor plastering 45% complete, septic tank slab wall rebar tie-in complete 80%, template installation 10%.
School 97: 98% of the interior wall repair brick wall completed, 98% of the second floor repair of utilities completed, 80% of the outdoor curtain wall plastering completed, 70% of the second coat of putty construction on the interior wall completed, 35% of the floor tiles affixed, 80% of the outdoor backfill construction completed, and 10% of the welding of the steel climbing ladder completed.
School 98: 88% of the interior wall patching brick wall completed, 85% of the second floor repairs of water and electricity completed, 98% of the second floor plastering of interior interior walls completed, 48% of the outdoor plastering completed, 100% of the waterproofing team's construction of patching the roof completed, 45% of the atrium's backfill soil backfill completed, 100% of the outdoor perimeter wall's foundation placement completed, the perimeter wall bricks entered the site, and 50% of the temporary septic tanks and ablution rooms outdoors completed.
School 105: plastering of the second floor stairwell completed 100%, 93% of the first floor interior wall putty construction completed, 85% of the interior wall repair completed, 75% of the water and electricity pre-embedded installation completed, 65% of the outdoor fence masonry completed, 100% of the outdoor curtain wall plastering completed, 70% of the first floor ceiling keel frame installation completed, 60% of the gypsum board ceiling completed, 60% of the curtain wall installation completed, and 30% of the exterior wall plastering completed. The installation of the first floor ceiling keel frame is completed by 70%, gypsum board ceiling is completed by 60%, curtain wall installation is completed by 60% and exterior wall plastering is completed by 30%.
School 106: 80% of the concrete pouring for the over-beam was completed, 40% of the steel reinforcement binding for the independent foundation of the outdoor perimeter wall was completed, 50% of the fixed mesh for the interior wall was completed, 50% of the plastering for the second floor of the interior was completed, 50% of the construction of the temporary outdoor septic tank and the washroom was completed, and 20% of the welding of the steel structure ladder was completed. The floor tiles of the first-floor workers' dormitory were 90% finished.
School 96: 90% completion of window installation for external wall plastering.
School 100: 80% of masonry on the second floor of the main building.
The Iraqi Model School project is working smoothly,safely and rigorously according to the construction plan.
The progress of the project continues to advance and some of the works have been completed on schedule.
The project team is making every effort to complete the project in anticipation of the blueprints turning into reality and
waiting for the flowers to blossom.