Show letter good, see words like a meeting ~ time is leisurely, family voice as expected, November letter along with the warmth of the early winter sun arrived, to share with you the latest developments and beautiful changes in the project. The project team of Américo Hospital in Angola adheres to the craftsmanship, and the construction site, with its unique rhythm, interprets the unceasing struggle from day to night. Over the past period of time, the project team has been working day and night, and we have made remarkable progress in the rapid advancement of our project. As night falls, the construction site does not fall silent, but rather ushers in another scene. The night lights are like daytime, illuminating every busy corner.
We would like to present the latest construction progress broadcast for our families:
Ameriko hospital project covers an area of about 3900 square meters, upstairs four floors, no basement, the main building of about 15600 square meters, the current progress: the foundation is completed 100% of the first floor to the second floor of the main body, columns, slab wall pouring is completed 100% of the first floor of the roof pouring of the square of about 3052 square meters, the completion of the progress of 72.8%
Construction Progress of Ameriko Hospital O Building O Building Function: Dormitory Building The O Building of Ameriko Hospital Project has a floor area of 3,378 square meters, with two upper and lower floors, 44 standard rooms, and public bathrooms, laundry, public cafeteria and recreation hall. Current progress: the main building area of 3,378 square meters has been fully completed interior secondary structure, masonry is completed 100% interior wall painting is completed 100% interior wall coating the first primer is completed 100% roof floor tiling has been completed. Total: 1,689 square meters of exterior wall painting is completed 100% of the first primer coat of exterior wall paint is completed 100% of the exterior wall paint is completed
All the members of the project department are united, hard work in the time of sharpening in the day and night in the polishing looking forward to the old building show “new face”.