Dear Hirojin Family:
See the letter~
This is a letter from the project department of the Iraqi cement plant thousands of miles away, which is currently under intensive construction, and we are here to present you with a letter from our family in March.
Project construction is a systematic and complex work
For more than half a year, we have faced many difficulties
All parties do everything possible to mobilize personnel,
financial and technical support
All the staffs are organized according to their specialties
Facing the challenges head on and solving them one by one
Here's a report on the progress of the project to the family:
In our daily work, we organize regular construction safety management meetings and progress meetings to continuously promote the project. It is now the rainy season, which makes the construction quite difficult. In order not to affect the construction progress, the project department is taking drainage measures and coordinating the construction work.
Completed and operational are the labor camps in Areas B, C and D, the Elegant House and Frame House dormitories in Area A, and the Owners' Camp.
To date, about 2 kilometers of water-stabilized pavement has been laid on the roads in the field.
Cement Batching Plant
This project is a frame structure with a total concrete structure height of 13.5 meters, divided into two floors. Currently, the construction has reached the second floor, the 13.5m column reinforcement formwork has been completed, the beam reinforcement has been accepted and passed, the formwork is being installed and reinforced, waiting for acceptance and pouring.
Pre-homogenization Yard for Auxiliary Materials/Gypsum/Mixed Materials
Concrete pouring for 1-30 axle grid foundation is completed, and earth backfilling is completed; concrete pouring for 2-11 axle track foundation is completed, now tying up track floor beam reinforcement and installing track and pre-buried parts; foundation for DLQ-1a 82m retaining wall has been poured to complete the bedding layer, and SLQ-2 retaining wall has been completed.
Heavy Oil Tank Foundation Project
This project is substantially complete, with the bulkhead within the firewall 70% complete. Both the medium coarse sand bedding and asphalt layers have been completed.
Limestone Pre-Homogenization Yard/Pure Limestone Depot
This project is now complete with the track girders poured as a whole, waiting for the installation unit process to be completed for the second pour, the gallery foundation is complete and the backfill process has been completed, and the remaining two column foundations at the end of the gallery awaiting construction due to weather conditions.
Next, according to the remaining amount of work, the project department will arrange the construction process in detail, try to organize the construction interspersed, concentrate on controlling the quality of the project, and make every effort to ensure the progress of the project.
Busy work should also pay attention to the combination of work and rest, it so happens that our construction environment is also a beautiful scenery, looking forward to the early presentation of the most "beautiful" works here.
People come from far and wide to form a team here
Some people for the love of the cause
Some for the glittering dream
And some for the heavy responsibility.
Since you have chosen a faraway place
We will continue to carry on with the spirit of Guangjin.
In the future, we will continue to uphold the spirit of Guangjin, with full vigor, side by side, and look forward to harvesting the fruits belonging to all of us as soon as possible.